Reliability Charge
What is Reliability Charge?
Firm Energy Obligation
Auction for the Allocation of the OEF
Firm Energy for the Reliability Charge
· Hydraulic Generation Plants
· Thermal Generation Plants
· Self-scheduled plants
·

Declaration of parameters

The Contingency Mechanisms
Settlement
Guarantees
Legal Basis (in spanish)
Transition
Documents for Consultation (in spanish)
Colombia and its Electricity Sector in Figures

> Related Links > Contact Us
This is an informative document and does not replace the regulation issued by the CREG.

Firm Energy for the Reliability Charge



To be able to participate in the auctions for the allocation of the OEF, it is necessary for the generator or investor to report to the CREG the parameters supporting its posterior declaration of ENFICC to enable the CND to verify the declaration.

Although there are various approaches to calculate firm energy, the CREG has established a methodology for each type of generation technology.


> See Chapter IV of the CREG Resolution 071 of 2006
> See ENFICC declared by generators and verified by the ASIC